Roof Top Solar

Key Points

  • Application fee is $300
  • Member-owner and other monthly fees are not offset by solar production
  • Maximum 20 kilowatts
  • Excess monthly generation is banked and rolled over monthly for 12 months (June to June)
  • Excess generation bank is zeroed after 12 months, therefore solar system should be right-sized

Needed from Customer

  • Interconnection Application & Agreement
  • Application fee of $300
  • Rider NM-RSC (2021 version) signed and dated by the member
  • Proof of insurance – minimum of $100,000
  • Specification sheets / one line diagrams of the installation stamped by licensed engineer
  • Inspection certification from the county

Contact Information

Email solar@mpd.coop or call 843-665-4070 for more information.  Lastly, you can visit the South Carolina Solar website for additional information and guidance.