Roof Top Solar

View Pee Dee Electric Cooperative’s Policy for Interconnection of Distributed Resources (PDF).

Key Points

  • Application fee is $100
  • Member-owner and other monthly fees are not offset by solar production
  • Maximum 20 killowatt
  • Excess monthly generation is banked and rolled over monthly for 12 months (June to June)
  • Excess generation bank is zeroed after 12 months, therefore solar system should be right-sized

Needed from Customer

  • Interconnection application
  • Application fee
  • Rider NM-RSC (2019 version) signed and dated by the member
  • Interconnection agreement
  • Proof of insurance
  • Specification sheets / one lines of the installation
  • Inspection certification from the county

Contact Information

Email Michael Humphrey or call (843) 292-4432 for more information. You can also email Kelly Blackmon or call (843) 292-4365. Lastly, you can visit the South Carolina Solar website for additional information and guidance.